Week 24 - Project Update

1 / 17
Connect Ramp Sanctuary To Church House
2 / 17
Existing Driveway Sidewalk And SanctuaryEntrance Closed
3 / 17
Interior Corridor Near New Childrens Chapel Tile Wainscoting In Place And Wall Being Prepped For Painting
4 / 17
Kitchen Plumbing Underground Rough Work To Be Completed By The End Of This Week Slab Expected To Be Constructed Week Of Aug 7
5 / 17
Lund Hall New Wood Floor Sleepers And Sub Flooring Commenced Electrical Work For Floor Outlets
6 / 17
Mail Box Has Been Moved Closer To Staff
7 / 17
New Curbing And Sidewalk Preparation On South Side Of Church House
8 / 17
New urbs And Planting Areas At CCK Entry
9 / 17
Old Step At Sanctuary Door
10 / 17
Propose To In fill Both Windows With Stone To Match Existing New Higher Grades Will Impact Old Window Openings Currently Boarded Up
11 / 17
Sub Flooring Material Delivered For Lund Hall
12 / 17
The Roofing Begins
13 / 17
Tile Work Started In CCK Corridor
14 / 17
Tree For The Parking Lot Are Delivered
15 / 17
Underground Piping For New Kitchen Layout Testing And Inspections This Week Place New Slab Floor On Aug 7
16 / 17
Window Trim At Lund Hall
17 / 17
Work Continues In Lund Hall