Projected Timeline

Inside Demolition Completed March 31 2017
Work Begins on the Vestibule area April 15 2017
Work Begins on the Enhanced
Entrance to the Sanctuary
April 30 2017
Groundbreaking ceremony April 30 2017
rain date May 7 2017
Work in Children's classrooms June - August 2017
Construction Completed (6 months) Before Rally Day 2017

Completed Projects

Ceiling fan installation in Sanctuary Completed
Sewer line work Completed
Finalize Construction Manager contract Completed
Complete construction drawings Completed
Bid out, select, and contract with subs Completed
Finalize Guaranteed Maximum Price Completed
A.P. Construction mobilizes Completed
Vacate Church House Completed
Construction begins Completed
Down Come The Trees Completed